Dear Autonians,
Please see the message below. Are there any deadlines I should be aware
before giving Ed green light to shut down electricity.
Predrag
-------- Original Message --------
Subject: Need Feedback - [Power Outage] SCS Wean Hall machine room
Date: 2017-02-09 10:04
From: Edward Walter <ewalter at cs.cmu.edu>
To: Edward J Walter <ewalter+ at cs.cmu.edu>
Hello,
SCS Computing Facilities is working with CMU FMS to schedule the final
round of work for our Wean Hall machine room - power expansion project.
This will involve provisioning approximately 11x high capacity circuits
to accommodate the influx of GPU servers and cluster expansions that is
expected to continue through 2017.
We're planning to schedule this work for the end of February or the
beginning of March. The outage is expected to take 1 business day and
will need to be scheduled mid-week (preferably on a Tuesday or
Wednesday).
If there are specific days/dates we should avoid (due to deadlines,
etc); please let us know ASAP so that we can coordinate this with FMS
and the electrical contractors.
Thank you.
-Ed
Affected clusters:
ACTR.HPC1.CS.CMU.EDU
AUTON
COMA.HPC1.CS.CMU.EDU
CORTEX.ML.CMU.EDU
LATEDAYS.ANDREW.CMU.EDU
MATRIX.ML.CMU.EDU
PSYCH-O.HPC1.CS.CMU.EDU
PERCEPTRON.RI.CMU.EDU
ROCKS.IS.CS.CMU.EDU
WORKHORSE.LTI.CS.CMU.EDU
YODA.GRAPHICS.CS.CMU.EDU
TRINITY.VISION.CS.CMU.EDU
Affected servers:
ACTR-SERVER
ARNOUT.ML
DENVER.LTI
DGX-1.ML
FLORIS.ML
GPUSERVER.PERCEPTION
GPUSERVER2.PERCEPTION
GPUSERVER3.PERCEPTION
GPUSERVER5.PERCEPTION
GPUSERVER6.PERCEPTION
GPUSERVER7.PERCEPTION
ISLR0S0
ISLR0S14
ISLR1S10
JAN.ML
LOR.LTI
LYSBET.ML
MARTEN.ML
MIAMI.LTI
PACIFIC.DB
SASKIA.ML
SLIF.COMPBIO
More information about the Autonlab-users
mailing list