<div dir="ltr">Dear Autonians,<div><br></div><div>I just finished provisioning two new GPU nodes. The purchase was approved by Dr. Schneider in July but the order was not placed until late August due to CMU internal issues just in time to be affected by supply chain disruption. The servers were finally shipped on 11/24/2021</div><div>and received last Wednesday 12/8/2021. To add the final insult to the injury the nodes were not tagged until Monday afternoon. I had literally to hunt down people to do the work.</div><div>I spent half a day yesterday getting power cables and other misc supplies. Thus they are only done today. However, I think they are definitely worth the trouble.  <br></div><div><br></div><div>Each server comes with 8 NVIDIA RTX A6000 connected by high-speed GPU interconnect NVIDIA links beside PCIe. Each server has 2 AMD EPYC 7502 32-Core Processors for a total of 128 threads per server. These CPUs are almost as fast as your desktop processors 3.5 GHz. </div><div>Each server has 512GB of RAM and 2TB of scratch. These servers have 24 2'5" HDD bays so they could potentially be used as a storage space. I don't have 2'5" HDDs in the lab right now to populate the bays.</div><div><br></div><div>There is one thing which is for now done suboptimally. Namely the servers were shipped with 1Gbs copper NIC and 10Gbs fiber optical NIC. I could not locate long enough optical cables in our lab yesterday but I will try to address this issue soon. I have exactly 2 optical connectors on the switch so it is down to cabling. </div><div><br></div><div>Have fun and sorry for a long delay.</div><div><br></div><div>Predrag</div></div>